Project Schedule
The project is currently divided into four broad phases. The schedule below shows the tentative fiscals years the project contracts might be awarded, which represents the year INDOT will encumber the money to fund the construction. 
Phase 1 (Awarded FY 2012 or 2013)
Adding travel lanes on I-465 from just east of US 31 to just east of Keystone Avenue. During this phase, the bridges at College Avenue and Westfield Boulevard and the Keystone Avenue interchange will be reconstructed.
Phase 2 (Awarded FY 2013 or 2014)
Continuing east, travel lanes will be added to I-465 from just east of Keystone Avenue to just east of 82nd Street. This phase includes the Allisonville Road interchange, as well as bridges at North River Road, East 82nd Street and the White River. Also included in this phase is the area south of 75th Street to just north of Fall Creek Road, including the bridges over east 71st and 75th streets.
Phase 3 (Awarded FY 2014 or 2015)
This phase includes the reconstruction of the interchange at I-465, I-69 and Binford Boulevard.
Phase 4 (Awarded FY 2015)
Travel lanes will be added on I-69 from just north of the I-465 interchange to the Marion County line, just south of 96th Street.